supported by bridle rings and/or J hooks. The MO/OSP Project Manager prior to installation must
approve all other support methods and/or materials. Cables shall be tied to permanent supports.
b) In order to assist vendors in understanding the SCS-CCTV Master Specifications, Design
c) Normally in new construction, the conduit with pull-strings and backboards for SCS-CCTV and terminal
cabinets for SCS-CCTV video data will be installed by the electrical subcontractor(s) to the general
contractor. In existing facilities, this work may be performed by M-DCPS electricians or by authorized
vendors. The SCS-CCTV vendor(s) shall carefully inspect the conduit work for adequacy and inform
the MO/OSP Project Manager of any needed changes or missing conduit, terminal cabinets or
backboards. In the event that conduit, terminal cabinets and backboards are required but have not
been supplied, the SCS-CCTV vendor(s) may also be responsible for installing conduit and backboards
along with the additional wiring, upon receiving prior written approval from the MO/OSP Project
Manager.
d) The vendors that will install the various SCS-CCTV components shall inspect the raceway infrastructure
and report any required changes to the MO/OSP Project Manager. The SCS-CCTV vendor, the
equipment vendor, and the MO/OSP Project Manager and construction Project Manager shall
cooperate with each other to resolve any problem involving raceway infrastructure.
e) It is agreed and understood that the installation work may require mechanical work such as removal of
ceiling tiles, drilling holes in walls and floors and similar changes to an existing building. Vendors shall
restore such disturbed areas to original condition conforming to M-DCPS Master Specifications. The
vendor at no cost to the Board shall replace ceiling tiles damaged by the vendor.
f) All SCS-CCTV cabling shall be concealed to the maximum extent practical. When retrofitting existing
systems, existing conduits, floor ducts and poles shall be used where possible, when authorized to do
so by the MO/OSP Project Manager. The vendor shall remove existing cabling and raceway as directed
by the MO/OSP project manager during the project site scope meeting.
g) At retrofit locations, the existing systems shall be maintained in operation to the maximum extent
possible while the new systems are being installed. It is understood that there may be reductions in
service and that various locations may be out of service while they are being replaced. It will be
necessary to cooperate with the building personnel to reduce interruptions to a minimum.
h) Prior to performing any work, the vendors and the Board's representative shall determine if any hazard
exists. If, during the course of the work, any unforeseen hazards are encountered, the vendor is to
immediately:
1) render the work area safe
2) cease all other work
3) contact the MO/OSP Project Manager or authorized
i) No PVC conduit shall be used above ground but may be installed underground (see M-DCPS Master
Specifications). If PVC is installed underground, it shall be no smaller than 1" diameter and shall be
schedule 40 type. Metal conduit shall be used at the end of underground PVC where the run leaves the
earth and enters a building if it enters through an outside wall and is exposed.
j) Conduit shall be mounted ten feet above the floor or as high as practical if the ten feet height is not
possible.
k) The types of conduit and the locations where each type may be used shall be governed by Miami-Dade
County Public Schools Master Specifications.
l) Supply and install EMT throated connectors, raceway bushings or bonding bushing as required by M-
DCPS installation specifications in each raceway terminations. All raceway bushings shall be in